Construction Update

  • Three 58m Luffing Jib cranes continue to construct all three buildings on site.
  • Floor plates have been poured to level 8 in Linter, level 10 in Carding and level 2 in Calico.
  • The cores in Carding and Linter are now fully topped out. Calico continues.
  • Bathroom pods have been installed to circa 180 apartments.
  • Installation of brick faced pre-cast concrete facades with glazing continues, as you can see in the accompanying images. Once fully established this process should continue at approximately one floor per week.
  • Internal apartment partitions have now commenced,  showing visible definition of apartments throughout the construction.

The most up to date progress can be found using our social media outlets – please feel free to follow, share and like.

If you have any questions or would like to enquire about current availability, please contact Rob Butler as follows:

rob.butler@eu.jll.com +44 161 200 1669 or +44 7710 965 668